Consultation is open from 3 August 2026 9:00am to 25 September 2026 5:00pm
Policy S/RRA/NW: Norman Way, Over
- Site area of 1.7 hectares
- Capacity for 6,100 square metres gross internal area of office (Class E(g)(i)), research and development (Class E(g)(ii)), light industrial (Class E(g)(iii)), general industrial (B2) and storage or distribution (B8) floorspace.
1. Development proposals must demonstrate how they will meet the following requirements:
- Siting, height, and design of buildings should respond positively to the local character and setting, ensuring no unacceptable adverse impacts on the wider setting of nearby heritage assets the Grade II listed Over Mill and scheduled monument Over Windmill;
- Development proposals should retain and enhance the treescape buffer within the southern and eastern sides of the site;
- Access to the site should be via the existing Norman Way road, and not an additional access onto Longstanton Road; and
- Development proposals must be accompanied by an appropriate archaeological assessment, including the extent, character and condition of the archaeological resource and the likely impact of the development on the archaeological remains.

Figure 96: Site Plan of S/RRA/NW: Norman Way, Over
Supporting information
3.5.25. This 1.7 hectare allocation comprises an area of undeveloped land within the Norman Way Industrial Estate, providing an opportunity to accommodate approximately 6,100 square metres of employment space that will positively respond to the character of the surrounding area, including the setting of nearby heritage assets Over Mill and Over Windmill. The retention and enhancement of the treescape will ensure that new development has a positive impact upon its wider landscape setting whilst site access will need to be managed through the existing industrial estate. Given the known archaeological assets in this area, further archaeological investigation and work will be required as part of any development proposal.
Tell us what you think
For further guidance on how to submit comments, please see the Representation Guidance Note.